Should we rip Ontario’s wind turbines out of the ground?

During the Ontario Progressive Conservative leadership race, candidate Tanya Granic Allen declared “I’m going to rip those turbines out of the ground!”  Many folks in rural communities suffering from health effects caused by those industrial wind turbines (IWT), and people who have trouble paying their electricity bills probably cheered that statement. They might have wondered what doing that would cost.

Let’s ponder that question and try to put a dollar figure on it!

The capital cost of IWT suggested by AWEA (American Wind Energy Association) was approximately US $1.3 million per megawatt (MW) which equates to about CDN $1.7 million/MW. IESO’s recently released 18th month Outlook Report (July 2018 to December 2019) indicates we have 4,400 MW (rounded) installed “grid connected” IWT and 600 MW of “embedded” IWT wind generation.  What that suggests is, the total capital cost of grid and embedded IWTs is in the neighbourhood of $6.5 billion.  In addition, there are outstanding contracts for another 375 MW.

Looking at the current installed capacity of 5,000 MW and a capacity factor of 30% those 5,000 MW should generate 13,140,000 MWh yearly. Now, assuming the average price paid for IWT-generated power is $135/MWh* (megawatt hour), those 5,000 MW would earn annual revenue of approximately $1.8 billion.  Over the 20-year term of the contracts they would result in revenue of about $36 billion.

Because of the unreliability of wind power** it must be backed up with natural gas plants. E.ON Netz Gmbh claimed in a 2005 Wind Report that a “back-up provision of 90% of the wind would be necessary”.  What that means is, the 5,000 MW of IWT require the back-up of 4,500 MW of natural gas plants.  Those gas contracts call for payment when idling in order to amortize the capital costs over the 20-year term of the contracts.  The approximate cost to ratepayers is $10,000/MW of capacity per month.  That back-up annual cost is approximately $600 million and over 20 years $12 billion.

That brings the annual cost of the 5,000 MW of IWT and its back-up of gas plants to about $2.4 billion. Not included in that $2.4 billion are costs for spilled hydro (6 TWh in 2017) or curtailed wind (3.3 TWh in 2017) which were spilled/curtailed due to wind generation presenting itself when unneeded. The latter two add another $650 million to the costs of IWT generation bringing the costs of the 9.2 TWh of IWT generation in 2017 to $3.050 billion. Grid accepted wind in 2017 was 9.2 TWh and gas generation was 5.9 TWh meaning collectively those 15.1 TWh cost ratepayers $202 million per/TWh or 20.2 cents/kWh (kilowatt hour)!

Based on the above, “ripping those turbines out of the ground” would mean spilled hydro alone could replace 65% of the grid accepted IWT generation. The remaining 9.1 TWh (wind + gas) could have been easily supplied by gas generation at a nominal cost of approximately $300 million.   The annual savings would be $1.5 billion without the IWT generation!  What that means is the IWT capital costs ($6.5 billion) could be repaid in under 4.5 years without considering the fact that many of them have depreciated in value since installation.

So, just maybe, this is an idea worth consideration. Rip the turbines out and pay the developers the capital costs, and refinance the monies over five years via our electricity bills.  I would suggest we call it the SDRC (Smitherman Debt Retirement Charge) to recognize the Ontario Minister of Energy who created the Green Energy Act.

The biggest obstacle to ripping the turbines out of the ground is the knowledge the contracts were written in favour of wind developers, not ratepayers. So, you could expect “ripping them out” would result in a myriad of lawsuits seeking full restitution for the remaining terms of the contracts, meaning the developers would seek to be paid the $36 billion noted above.

My recommendations are simple:

  1. Cancel the wind power projects in process (375 MW) awaiting the REA from the MOECC or those being fought before the ERT (Environment Review Tribunal) and the Ontario court system and
  2. Tax the hell out of those already up and running.

Parker Gallant

*The average cost is actually higher as all of the FIT contracts contain escalation clauses allowing for annual increases equal to the cost of living escalation to a maximum of 20% or $27.per MWh.

**IESO’s 18th Month Outlook report forecasts IWT capacity at peak demand periods at only 13.8% and a peer reviewed paper by Marc Brouillette indicates IWT only produce power of value to the grid 35% of the time they are generating power.

Advertisements

12 thoughts on “Should we rip Ontario’s wind turbines out of the ground?”

  1. The idea certainly works from a financial perspective but it does not address any of the other issues. The regulations fail to include infrasound, low frequencies, high frequencies, amplitude modulation, stray voltage, vibration, the trespass of shadow flicker, the destruction of prime agriculture lands, disturbances to water wells, impact on livestock and wildlife harm/harassment/kill/ displacement

    Liked by 2 people

  2. Once the general public sees this presentation given by Professor Mariana Alves Pereira recently in Slovenia, they will understand why the turbines need to be turned off now.

    Liked by 2 people

    1. The cease-to-operate turbines in Ontario is the only solution to begin the restoration of health, environment, social and economic stability. When an (il)legal legislation wipes out 21 Acts in order to be enacted, the damage that is permitted is on a scale of epic proportions.
      When the Wind Industry has a record of buying out homes for harm, noise and non-compliancy why is the Wind Industry permitted to continue to cause harm? Because we put an act through legislation (The Crown) to permit the destruction. Follow The Money!
      The Liberals & The GEA 2009 has:
      Failed to protect the environment.
      Failed to protect human health.
      Failed to do a value for money audit.
      Failed to do a cost benefit analysis.
      Failed to enforce non-protective, wind lobbiest regulations.
      Failed to protect prime agriculture lands.
      Failed to tax appropriately the asset of the Wind Industry. (turbines are under valued for a reduction in taxes). I don’t see them undervaluing our home to save home owners money … Instead MPAC has ruled the infrastructure from IWT’s an asset and increased my property taxes. I’m a non-participating receptor.
      Failed to investigate thousands of pollution reports.
      Failed to mitigate.
      Failed to report to the REDA.
      Failed to investigate well damage.
      The Green Energy & Economy Act 2009, with its Liberal Government and the legislated regulator Agencies are a disastrous failure.
      FAILED.

      Like

  3. “tax the hell out of those already up and running.”

    Yes, tax or some overt penalty, on the basis of the disruption they cause and the costs they impose on the system.

    And absolutely yes cancel those that were in the pipeline at election time.

    Caveat venditor. Perfectly reasonable legal principle.

    Like

  4. One better, the government should pass a limited liability law, that states that projects that are deemed not to be in the public interest May be cancelled with the governement only responsible for just a resonable cost incured up to the cancellation date and resonable costs to shut down the project. And no governement contract should ever include any cancelation fee.

    Like

  5. As always, great analysis and recommendations. Still, there might be something emotionally gratifying about ripping out at least a few turbines. You could sell tickets.

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s