The political web of EDPR and the Nation Rise wind power project

 

The power from Nation Rise would be like a fly on an elephant in terms of Ontario demand. Cancelling would save hundreds of millions.

Last week, a news article appeared in the Nation Valley News reporting the local Conservative MPP, Jim McDonell’s response to a question asking on why the government hasn’t cancelled the 100-MW Nation Rise wind power project. Mr. McDonell said, “We’ve always been clear: We would cancel any project we could cancel economically,” and he added “… we just can’t spend a billion dollars to cancel a project and get nothing from it.”

The same day, a press release from the Ford government noted that Premier Doug Ford told people attending the annual Rural Ontario Municipal Association (ROMA) conference, that “We’re lowering electricity costs”

I am at a loss to explain Mr. McDonell’s suggestion that cancellation of the Nation Rise IWT project would cost the same as the McGuinty/Wynne gas plant moves, but that’s what he said. It’s worth a look back at how this power project came into being, as it illustrates the disaster that has been Ontario energy policy for the last 15 years.

The Nation Rise wind project was one of five awarded contracts in March 2016; after that, its history gets really interesting … and very political.

Cost of the project

The Independent Electricity System Operator (IESO) at that time noted the average price for all the projects proposed was $85.90/MWh (or 8.5 cents per kWh). Over 20 years that would produce revenue of about $450 million, or less if their bid was lower than the average..

If the project were cancelled, no court would award them the full contract amount; it is more likely the government would be on the hook for perhaps 5 to10 % of that amount (on the high side).

There is no doubt that cancelling this project would save Ontario citizens hundreds of millions.

Timing of the approval

According to the Environmental Registry the Nation Rise entry for the Renewable Energy Approval or REA is dated May 7, 2018 and indicates it was loaded to the registry May 4, 2018.  That is just four days before the writ was drawn up by former Premier Kathleen Wynne, formally announcing the upcoming Ontario election.  It was known* the voting date would occur on June 7, yet the REA — a major decision — was given by the Ministry of the Environment and Climate Change (MOECC).  At that time, not only were polls forecasting a defeat for the Liberal government, “electricity prices” and hydro bills were a major election issue. The MOECC issued the decision anyway.

Is the power needed?

In 2015 (before the IESO called for more wind power proposals) Ontario had a huge surplus of generation. Our net exports (exports less imports) were 16.8 TWh (terawatt hours) or enough to supply almost 1.9 million average households (over 40% of all Ontario households) with their electricity needs for a full year.  It cost ratepayers an average of 10.14 cents/kWh to generate that power which was sold for an average 2.36 cents/kWh, representing a cost of $1.3 billion to Ontario’s ratepayers.

Due to the highly intermittent nature of output from wind turbines, the IESO’s projections of long-term capacity use only 12% of the nameplate capacity for wind power installations when calculating their contribution to overall capacity. So for Nation Rise, the IESO is projecting that the useable contribution of the project will be 105,120 MWh — just .0765% of the IESO’s forecast power consumption of 137.4 TWh. That is a fly on the flank of an elephant, in my estimation.

Cancellation of Nation Rise would not affect the long-term supply of electricity for the people of Ontario.

Worse, adding more capacity, particularly from an intermittent source, could result in more spilling of hydro, more curtailment of wind power generation, additional nuclear shutdowns or steam-off, all of which would drive Ontario’s electricity bills rates higher.

Property value loss

The property losses in value caused by the presence of 33, 650-foot industrial wind power generators throughout the countryside in the Nation Rise project will be in the tens of millions of dollars according to a study which notes: “Using research completed recently by a land economist with the University of Guelph and published in Land Economics, Wind Concerns calculates that overall, the property loss for houses within 5 km of the 33 planned turbines could be $87.8 million. Using other research that is less conservative, however, the property value loss could be more than $140 million.”

A loss of either magnitude would impact North Stormont’s realty tax base leading to either significant drops in revenue for the township or realty tax increases as a multiple of the COL (cost of living).

And then there’s the water

One condition among many in the REA given to EDP/Nation Rise was related to identifying and mapping all water wells in the project area within a set range of any proposed equipment, meteorological tower or wind turbines. This was due to concerns about construction activities on the local aquifer. While EDP identified 444 wells, the community group says there are more than 800 homes within the immediate project. Water wells in other areas of Ontario and elsewhere have become contaminated allegedly due to drilling and vibrations from wind turbines. There is significant concern about contamination of the wells, and the assessment taking place.

North Stormont is dairy farm country, and each farm operation uses thousands of litres of water every day — what would be the effect on these businesses, and Ontario’s food supply, if suddenly, the water wells were not functioning?

Who is EDP?

EDP (parent of EDPR) is a Portuguese utility company partially owned by two of the Chinese government’s companies; China Three Gorges (23.27%) and CNIC Co., Ltd., (4.98%) and the former has been trying for several years to acquire the balance of the shares. That attempt is speculated to be off; however, a recent NY Times article suggested otherwise, based on discussions with Portugal securities regulator CMVM.

Where is democracy?

North Stormont, where the Nation Rise wind project is planned, declared itself an “unwilling host” in 2015, well before the award of the contract or the issuance of the REA. The people perhaps relied on promises made by former energy minister and Ottawa Liberal MPP, Bob Chiarelli, when in 2013 he declared: “It will be virtually impossible for a wind turbine, for example, or a wind project, to go into a community without some significant level of engagement”. Despite their council passing the unwilling host motion, and also joining the 117 Ontario municipalities demanding a return of local land-use planning for energy projects, the IESO still granted Nation Rise the contract.

There are many questions about this project and many reasons why it simply isn’t needed. Cancelling this contentious project is a perfect way to lower future electricity costs, directly.

PARKER GALLANT

*The Toronto Star reported in an article dated October 19, 2016 the next Ontario election would be on June 7th, 2018

 

Author: parkergallantenergyperspectivesblog

Retired international banker.

10 thoughts on “The political web of EDPR and the Nation Rise wind power project”

  1. Thank you Parker for looking at this situation from so many different angles. You say, “Using other research that is less conservative, however, the property value loss could be more than $140 million.”

    A loss of either magnitude would impact North Stormont’s realty tax base leading to either significant drops in revenue for the township or realty tax increases as a multiple of the COL (cost of living).”
    Would you be able to give an estimate of the “realty tax base”losses and “drops in revenue” or “realty tax increases” relative to COL, in the rural communities in Ontario where projects that are still running and could run their course, unless these contracts are cancelled?

    Like

    1. I would need a team of research assistants to do as you suggest. It could be an interesting issue for a university group studying economics to work on though. One would need to look at each community/municipality and their individual mill rates which are different in each and every one. That study would also entail the finding of the location of each turbine and its proximity to households etc. on a uniform basis for all locations. A big job!

      Like

  2. THANK YOU for this article and the information. Really appreciated. Ruby

    On Mon, Feb 4, 2019 at 4:42 PM Parker Gallant Energy Perspectives wrote:

    > parkergallantenergyperspectivesblog posted: ” Last week, a news article > appeared in the Nation Valley News reporting the local Conservative MPP, > Jim McDonell’s response to a question asking on why the government hasn’t > cancelled the 100-MW Nation Rise wind power project. Mr. McDonell sa” >

    Like

  3. Hi Parker, Is the short story this project will cost ON taxpayers and ratepayers $450M, but could be cancelled now for between $23 and $45M, thereby saving over $400M and preserving the real estate values and water wells?? Are the PC’s spooked by stories of what Ford’s costing us, rather than what it’s costing us paying out these contracts full term? Thanks, Mike

    Like

      1. Based on what you’re saying about Nation Rise, is it logical to extrapolate that cancelling all contracts in Ontario now, would reap significant financial benefits for the province?

        Like