June 4th; Just Another day of Generosity by Ontario ratepayers and taxpayers

Well, once again, Ontario’s electricity generators were producing power we didn’t need. Nevertheless, the ratepayers and taxpayers of Ontario were obliged to give it away to our neighbours in Michigan, Quebec and New York.  This is a regular occurrence during the Spring and Fall seasons as demand is generally at the lowest levels for us but the GEA (Green Energy Act) imposed by the Liberal government during the McGuinty/Wynne years declared wind and solar generation were the future so they gave them contracts with very high rates and “first-to-the-grid” rights!

Ontarians have been paying the price for over a decade and despite the fact Liberals were found guilty of their stupidity on the electricity file and booted out of power, the current and recently reelected Ford led Conservative Party has done nothing to change things over their prior four years of power!

So, Saturday the fourth of June was simply another example of how the mess continues!

Peak demand in Ontario occurred during the 18th hour and peaked at 14,437 MW. Nuclear and hydro alone at that hour generated 14,631 MWh so wind and solar were not needed but those damn contracts stand in the way. At that hour wind was operating at 16.9% of their capacity and they could have peaked at 45% of their capacity at 1 AM but IESO (Independent Electricity System Operator) had them curtail 1,200 MW. 

IESO were busy selling off our surplus power throughout the day to our neighbours and did so with slightly over 24,000 MWh to Michigan, 22,300 MWh to Quebec and about 12,000 MWh to NY!  That power was sold at the astronomical (sarcasm intended) average HOEP (hourly Ontario energy price) of $6.34/MWh.

What the preceding tells us is we are giving Michigan and New York, clean green power to help then keep energy costs low and reduce their emissions. Quebec benefits by not using their hydro generation which they have presold to US States like NY under lucrative contracts.  No benefit for Ontario’s ratepayers or taxpayers as the following outlines!

If we simply assume the approximately 58,000 MWh, we exported earned us only $368,000 (58,000 MWh X $6.34/MWh), we should consider what it cost us!

The mix of electricity sold presumably included wind generation (26,000 MWh including curtailed), solar, hydro, nuclear and perhaps even a little natural gas. The minimum cost was approximately $116/MWh based on the GA (Global Adjustment) estimate by Scott Luft and the 2nd estimate by IESO for May and includes the $30/MWh taxpayer subsidy. Using the $116/MWh the cost of those exports becomes $6,728,000 and including the 4,900 MWh of curtailed wind total costs rise to over $7.3 million.  So, for what cost Ontario ratepayers/taxpayers $7.3 million we received less than $400K.

What the foregoing points out to the politicians in charge is that there is something inherently stupid with the way our electricity system is managed. We changed the political parties once because of the electricity file but the Ford government simply shifted a large part of the costs to the taxpayers so it was hidden from sight.

Perhaps the next election will be focused on the provincial debt and include the costs the Ford led government hid inside our Provincial debt.

If they actually do something to sort out the mess created by the Liberals it could reduce the provincial deficits by $6.9 billion as reported by the FAO of Ontario assuming they can keep electricity costs flat, perhaps by taxing the intermittent and unreliability of that expensive and harmful wind generation.

Only time will tell!

Author: parkergallantenergyperspectivesblog

Retired international banker.

6 thoughts on “June 4th; Just Another day of Generosity by Ontario ratepayers and taxpayers”

  1. This is an old chestnut that you have been hammering at for years.
    Suggest a fix. Then, move on to something else.

    Like

  2. Excellent illustration. If there was affordable, reliable storage this wouldn’t be as much of an issue but we don’t have that technology in place. So we continue to put the horse before the cart with short sighted energy policies. And we won’t have the storage needed for many years yet since the technology is still being developed.

    Like

  3. The ‘answer’ lies in the contracts. Ford/Phillips ‘comprehensive’ review concluded with the only way out was pay-to-term. Hence the cost transfer to tax base. Schreiner campaigned on pivoting the $7B annual subsidy ($4B if he left the means tested programs intact) to ‘green’ initiatives. Could he have declined to pay the developers subsidies? If so why doesn’t Ford?

    Like

Leave a comment