One (megawatt) is the loneliest number

On one day recently, for one hour, Ontario’s thousands of towering wind turbines delivered just one megawatt of power. And still, Ontario  had a surplus that was sold off cheap.

May 27 was a Saturday which is usually a “low demand” day for electricity in Ontario, compared to weekday power demand and assuming weather patterns are close to average. The temperature on the recent May 27 was slightly below historic averages in Toronto; as people woke up and set about their activities that day, the demand for electricity built slowly.

According to the IESO’s (Independent Electricity System Operator) Daily Market Summary, Ontario demand peaked at 14,069 MW and averaged 12,751 MW (total Ontario demand was 306,024 MWh for the whole day).  If anyone checked IESO’s “Power Data” page at, say, just after 11 AM, they would have noted demand was 13,208 MW at 10 AM and the HOEP (Hourly Ontario Energy Price) was indicating a negative price of -$4.00 /MWh.   If one had also looked at the “Generator Output and Capability” and scrolled down to “Wind Total” they would have seen that under the heading “Output” the number appearing on the screen was “1”!

As in, one single megawatt of power.

About half the capacity of one ordinary wind turbine.

So, at 10 AM on May 27, 2017 the approximately 4,500 MW capacity of the more than 2,000 wind turbines installed throughout the province by the McGuinty/Wynne governments with lucrative, 20-year contracts, were delivering one megawatt of power.

And yet, to the best of my knowledge, Ontario didn’t experience a blackout or brownout because intermittent wind power generation was almost completely absent, nor did our emissions increase, as we got all the power needed from nuclear and hydro resources.   In addition, the almost 9,000 MW of gas generation was idling, operating at an average of about 2% of capacity almost all day.

Despite wind only producing an average hourly output of 75 MW for the day and just the “1” for hour 10, Ontario still exported 43,584 MW of power at a cost to ratepayers of $5.6 million*.

Despite the lackluster performance of industrial wind turbines May 27 and on many other occasions, a visit to the home page of CanWEA still claims:  “Wind is delivering clean, reliable and low-cost electricity”!

Sure!

Perhaps with another 4,500 MW of capacity in Ontario, the industrial wind turbines may have delivered TWO MW of power at 10 AM on May 27?

 

*Cost estimate assumes the second IESO estimate of May’s Global Adjustment of $127.76 holds up.